Aqua Nat’Our, Luxembourg
The project was accepted after a proposal concept had been developed together with the municipalities involved, which are also the owners of the plant. Kannewischer Ingenieurbüro AG supervised, co-planned and developed all project phases of the facility, including a detailed space and area programme with economic efficiency forecast and preparation of the tender for the general contractor. Since 2013, Harald Kannewischer has been the operator of the facility under a lease agreement.
The project shows how we can lead a project from start to finish. The experience we learn every day in our own operation allows us to advise and plan future projects even more reliably.
Owner
Aqua Nat’Our
Architect
Krummlauf Teske Happold Architekten GmbH
D- 74076 Heilbronn
Period
Realisation 2011-2013
Nature of the building project
New building
Type of building
Swimming pool, Gym, Spa
Our Services
- Concept for heating, ventilation, sanitary, pool water systems, building automation and stainless steel basin
- Space and area program for total contractor bidding
- Tender for total contractor incl. selection procedure
- Quality assurance for heating, ventilation, sanitary, pool water systems, building automation and stainless steel basin
- Coordination of the overall building process
Trades
Heating
Ventilation
Sanitary
Pool water systems